Paediatric Intensive Care Unit and High Dependency Unit, Glasgow
Project
- Construction value: £3.6m
- Refurbishment and extension to existing operational hospital.
- Provision of 28 intensive care/high dependency beds.
- 1,825m² of modern facilities for the treatment of young children.
The approach
- Provision of pre and post contract cost management.
- Value engineering and life cycle cost advice.
The challenges
- Refurbishment and extension of a land locked site.
- Working above and below existing operational theatres, wards and kitchens.
- Highly serviced building.
Outcome
- Robust cost plan that achieves client’s aspirations.
- Thorough change control procedure to stringently manage post contract variations.