Redrow Homes - Velocity, Leeds

Project

  • New build development of 240 city centre apartments on a brownfield remediated site in Leeds.
  • £16 million guaranteed maximum price contract, with phased completion of apartment blocks.

The approach

  • The provision of project management, cost management and planning supervisor services.
  • The appointment of a partnered contractor into the development team, permitting a positive impact into the design development.

The challenge

  • Project delivery within the phased completion timescales and to budget.
  • Working with the adjoining developer to ensure the provision of the joint infrastructure.

Outcome

  • Project was delivered in 2004, ahead of programme and within budget.
  • Redrow achieved 100% sale of apartments before project completion.