Redrow Homes - Velocity, Leeds
Project
- New build development of 240 city centre apartments on a brownfield remediated site in Leeds.
- £16 million guaranteed maximum price contract, with phased completion of apartment blocks.
The approach
- The provision of project management, cost management and planning supervisor services.
- The appointment of a partnered contractor into the development team, permitting a positive impact into the design development.
The challenge
- Project delivery within the phased completion timescales and to budget.
- Working with the adjoining developer to ensure the provision of the joint infrastructure.
Outcome
- Project was delivered in 2004, ahead of programme and within budget.
- Redrow achieved 100% sale of apartments before project completion.