Paediatric Intensive Care Unit and High Dependency Unit, Glasgow

Construction value: £3.6m. Refurbishment and extension to existing operational hospital. Provision of 28 intensive care/high dependency beds. 1,825m² of modern facilities for the treatment of young children.

Provision of pre and post contract cost management. Value engineering and life cycle cost advice. The challenges: Refurbishment and extension of a land locked site, working above and below existing operational theatres, wards and kitchens, highly serviced building. Outcome: Robust cost plan that achieves client’s aspirations, thorough change control procedure to stringently manage post contract variations.